Boston, MA Abbot Building Restoration Co. completed a major repair and restoration of a brick and poured reinforced concrete building owned by Wentworth Institute of Technology in the Mission Hill section of the city. The building, 66 Louis Prang St., was formerly an old bus garage adjacent to Wentworth property that the owner purchased and was originally using for storage of excess miscellaneous equipment.

In 2015, the owner decided to renovate exterior of the structure (and eventually the interior) with the goal to move the school’s facilities department into the building. After a competitive bidding process, the owner, acting at its own consultant, awarded the exterior masonry contract to Abbot.

Abbot’s evaluated the building and identified the following major deficiencies:

• The brick masonry was extremely dirty

• The window were sills deteriorated and in some cases non-existent

• Brick above the windows to the roof had deflected and was no longer in plane with walls

• The windows were non-existent and filled with concrete block

One of the most significant repairs involved the removal of the concrete blocks that had been installed to secure the building from vandalism. When it was decided to turn the building to usable space, all of the blocks would have to be removed and new windows installed to provide ample light emission into the space.

Abbot also recommended that the brick veneer be removed from the top of the windows to the roof line, and would resource and install new brick to match the color of the rest of the exterior brick.

Based upon this comprehensive evaluation, Abbot performed the following sequence of repairs:

• All brick was power washed with a restoration cleaner to remove existing dirt, and paint was removed from bottom of perimeter of building to provide for a natural brick appearance

• All brick joints were repointed

• All of the bricks were removed from the top of the windows to the roof line, and entirely rebuilt using new matching brick

• The concrete blocks were removed from all windows

• New pre-cast concrete window sills were fabricated and installed to replace deteriorated and non-existent sills,

• New key stones were installed in the parapet corners to decorate the walls

• New energy efficient windows with security screens were installed

• The foundation and balance of the existing poured concrete was coated with an elastomeric material to improve the building’s appearance

• Finally, a new precast front sign was fabricated to match the original sign.

READ ON THE GO
DIGITAL EDITIONS
Subscribe
READ ON THE GO
DIGITAL EDITIONS
Subscribe
STAY INFORMED FOR $9.99/Mo.
NEREJ PRINT EDITION
Stay Informed
STAY CONNECTED
SIGN-UP FOR NEREJ EMAILS
Newsletter
Columns and Thought Leadership
Shawmut Design and Construction breaks ground on the 195 District Park Pavilion in Providence, RI

Shawmut Design and Construction breaks ground on the 195 District Park Pavilion in Providence, RI

Providence, RI Shawmut Design and Construction celebrated the ceremonial groundbreaking for the 195 District Park Pavilion, marking the start of construction on a facility that will feature year-round dining and support space for park operations. In addition to the 3,500 s/f building, the project will include infrastructure upgrades
The New England Real Estate Journal presents<br> the First Annual Project of the Year Award! Vote today!

The New England Real Estate Journal presents
the First Annual Project of the Year Award! Vote today!

The New England Real Estate proud to showcase the remarkable projects that have graced the cover and center spread of NEREJ this year, all made possible by the collaboration of outstanding project teams. Now, it's time to recognize the top project of 2024, and we need your vote!
Investing in a falling rate environment - by Harrison Klein

Investing in a falling rate environment - by Harrison Klein

Long-term interest rates have fallen by 100 basis points, and the market is normalizing. In December of 2022 I wrote an article about investing in a high interest rate, high inflation market. Since then, inflation has cooled off, and the Fed has begun lowering their funds rate.
The 2024 CRE markets: “The Ups” (industrial) and “The Downs” (Boston class B/C office) - by Webster Collins

The 2024 CRE markets: “The Ups” (industrial) and “The Downs” (Boston class B/C office) - by Webster Collins

The industrial markets have never been stronger. What has happened is that the build out of Devens with new high-tech biotech manufacturing with housing to service these buildings serves as the connector required to really make the I-495 West market sizzle. Worcester has been the beneficiary