Boston, MA Abbot Building Restoration Co. completed a major repair and restoration of a brick and poured reinforced concrete building owned by Wentworth Institute of Technology in the Mission Hill section of the city. The building, 66 Louis Prang St., was formerly an old bus garage adjacent to Wentworth property that the owner purchased and was originally using for storage of excess miscellaneous equipment.

In 2015, the owner decided to renovate exterior of the structure (and eventually the interior) with the goal to move the school’s facilities department into the building. After a competitive bidding process, the owner, acting at its own consultant, awarded the exterior masonry contract to Abbot.

Abbot’s evaluated the building and identified the following major deficiencies:

• The brick masonry was extremely dirty

• The window were sills deteriorated and in some cases non-existent

• Brick above the windows to the roof had deflected and was no longer in plane with walls

• The windows were non-existent and filled with concrete block

One of the most significant repairs involved the removal of the concrete blocks that had been installed to secure the building from vandalism. When it was decided to turn the building to usable space, all of the blocks would have to be removed and new windows installed to provide ample light emission into the space.

Abbot also recommended that the brick veneer be removed from the top of the windows to the roof line, and would resource and install new brick to match the color of the rest of the exterior brick.

Based upon this comprehensive evaluation, Abbot performed the following sequence of repairs:

• All brick was power washed with a restoration cleaner to remove existing dirt, and paint was removed from bottom of perimeter of building to provide for a natural brick appearance

• All brick joints were repointed

• All of the bricks were removed from the top of the windows to the roof line, and entirely rebuilt using new matching brick

• The concrete blocks were removed from all windows

• New pre-cast concrete window sills were fabricated and installed to replace deteriorated and non-existent sills,

• New key stones were installed in the parapet corners to decorate the walls

• New energy efficient windows with security screens were installed

• The foundation and balance of the existing poured concrete was coated with an elastomeric material to improve the building’s appearance

• Finally, a new precast front sign was fabricated to match the original sign.

MORE FROM Owners Developers & Managers

Mount Vernon Co. acquires John Carver Inn & Spa in Plymouth, MA

Plymouth, MA The Mount Vernon Company (MVC), a Boston-based real estate and hospitality investment firm, has completed the acquisition of the John Carver Inn & Spa, an 80-room property.
READ ON THE GO
DIGITAL EDITIONS
Subscribe
Columns and Thought Leadership
IREM President’s Message: Fostering community connections during the holiday season

IREM President’s Message: Fostering community connections during the holiday season

The holidays are again taking center stage, and with them comes an opportunity for multifamily communities to connect with the businesses and organizations in their cities and towns, fostering a sense of unity and generosity during this giving season
Selecting the right façade installation firm - by Steven Powell

Selecting the right façade installation firm - by Steven Powell

As the owner of a major new property being developed, or an existing large building preparing for major renovation, you want your design and construction team to have the right experience, capabilities, and expertise to match the project demands. A critical member of this team will be the façade installation specialty firm, since the quality of this installation will impact
Recently passed legislation creates opportunities to meet CT’s changing energy needs - by Klein and Feinn

Recently passed legislation creates opportunities to meet CT’s changing energy needs - by Klein and Feinn

For decades, New England has had a summer-peaking power system, where the greatest energy use occurs on the hottest and most humid days, due to widespread use of air conditioning. But by the mid-2030s, electrification of the heating sector likely will result in a winter peak that’s higher than the summer peak.