G. Greene Construction completes imaging suite at Mass. General

 

 

Boston, MA G. Greene Construction completed a five-phase imaging suite at Massachusetts General Hospital’s Yawkey Outpatient Care Center at 32 Fruit St. 

The imaging suite was constructed in a fully operational clinical space. Included in the new suite was a 3T MRI with a control room and two CT Scans. New corridors, with separate patient and staff access, waiting rooms, changing rooms, and administration support spaces were also constructed.

Including the Mass. General Hospital staff of the imaging suite in meetings was essential. They know first-hand how anxious the patients they care for everyday can be. To reduce patient anxiety, the team carefully selected and applied finishes and perimeter lighting with variable color schemes. To create a calming and relaxing environment, MRI-safe video screens were installed, which provide a pleasant distraction. A backlit ceiling panel was created which stimulates a view of the sky above patients to ease the feeling of intimidation patients’ often feel.

One of the most critical phases of this project was hoisting the Siemens 3T MRI, 4’-0” x 8’-0” x 8’-0” in size, weighing 18,000 lbs. to the 6th floor. The MRI was hoisted up 100 feet through a narrow 14-foot space between two buildings. Due to this challenging process, safety requirements were essential for both the workers and pedestrians to walk to their destinations out of harm’s way.  Numerous meetings with members of the rigging team, G. Greene, Mass. General, and abutters, were held at which time the safety plan was developed, modified, and finalized.  When faced with the challenge of hoisting the MRI into an occupied healthcare facility, six floors up, G. Greene was able to come up with a plan to ensure patients, staff, workers and pedestrians were protected.

The goal throughout the duration of the project was to ensure the staff had an efficient new department to care for their patients in a pleasing and calming environment, while providing a safe and well-organized construction site. Collaboration among G. Greene, Mass. General, and Payette, was essential.

READ ON THE GO
DIGITAL EDITIONS
Subscribe
READ ON THE GO
DIGITAL EDITIONS
Subscribe
Quick Hits
STAY INFORMED FOR $9.99/Mo.
NEREJ PRINT EDITION
Stay Informed
STAY CONNECTED
SIGN-UP FOR NEREJ EMAILS
Newsletter
Columns and Thought Leadership
Shawmut Design and Construction breaks ground on the 195 District Park Pavilion in Providence, RI

Shawmut Design and Construction breaks ground on the 195 District Park Pavilion in Providence, RI

Providence, RI Shawmut Design and Construction celebrated the ceremonial groundbreaking for the 195 District Park Pavilion, marking the start of construction on a facility that will feature year-round dining and support space for park operations. In addition to the 3,500 s/f building, the project will include infrastructure upgrades
The New England Real Estate Journal presents<br> the First Annual Project of the Year Award! Vote today!

The New England Real Estate Journal presents
the First Annual Project of the Year Award! Vote today!

The New England Real Estate proud to showcase the remarkable projects that have graced the cover and center spread of NEREJ this year, all made possible by the collaboration of outstanding project teams. Now, it's time to recognize the top project of 2024, and we need your vote!
Investing in a falling rate environment - by Harrison Klein

Investing in a falling rate environment - by Harrison Klein

Long-term interest rates have fallen by 100 basis points, and the market is normalizing. In December of 2022 I wrote an article about investing in a high interest rate, high inflation market. Since then, inflation has cooled off, and the Fed has begun lowering their funds rate.
The 2024 CRE markets: “The Ups” (industrial) and “The Downs” (Boston class B/C office) - by Webster Collins

The 2024 CRE markets: “The Ups” (industrial) and “The Downs” (Boston class B/C office) - by Webster Collins

The industrial markets have never been stronger. What has happened is that the build out of Devens with new high-tech biotech manufacturing with housing to service these buildings serves as the connector required to really make the I-495 West market sizzle. Worcester has been the beneficiary