Construction safety planning and our new normal - by Rebecca Jablonowski

New rules, new regulations, and a new deck of cards have been handed to us—and are changing how we manage projects as owner’s project managers (OPMs).

Rebecca Jablonowski

Construction projects are resuming, but will require new management innovations and safety oversight. The lens we use to view safety on jobsites will never be the same.

Logistics development and review
A new view of logistics planning now includes details on social distancing, testing of workers upon entry to jobsites, and material deliveries. The standard of having the contractor create a logistics plan at the time of bid should now be adjusted for a team approach to development with involvement by infection control experts.

Planning and protocol creation
Every state will have new requirements. In Massachusetts, for example, each contractor is tasked to create a significantly more robust safety plan focused on COVID-19 best practices. This new plan will be submitted to the Commonwealth for approval prior to mobilizing workers.

Tools and innovations
With the need for change comes innovation. Architecture, engineering, and construction (AEC) companies large and small are developing cutting edge technologies to meet the need of the new requirements. As owners’ representatives, Stantec has a unique opportunity to pair clients with the right team members to bring those innovations onto projects.

Implementation of safety plans and compliance surveys
The new safety requirements are created, submitted, and approved. Now what? The next step is for clients to partner with organizations to oversee implementation and conduct regular compliance surveys to ensure the plan is being maintained.

COVID-19 cost impact and project budgeting
In this time of uncertainty one thing is for sure, the new requirements will result in a new way to control procurement. Lengthened schedules, more dedication from safety managers, supply chain impacts, and additional site cleaning are just a few of the list of items to be added to bids, and the costs are very real. As we continue to track and evaluate cost impacts from our construction manager partners, we can inform the total project budget with the necessary owner-controlled risk contingencies and advise on appropriate sunset dates.

Rebecca Jablonowski is a project executive at Stantec, Boston.

MORE FROM Construction Design & Engineering
Construction Design & Engineering

Weston & Sampson earns award from ACEC for Arlington DPW job

Arlington, MA Weston & Sampson Engineers, Inc., has earned a National Recognition Award for exemplary engineering achievement in the American Council of Engineering Companies’ (ACEC) 58th annual Engineering Excellence Awards (EEA). The award comes for leading the renovation of the Arlington Department of Public Works (DPW) facility.
READ ON THE GO
DIGITAL EDITIONS
Subscribe
Columns and Thought Leadership
Ask the Electrician: Is summer a prime time for commercial electrical maintenance?

Ask the Electrician: Is summer a prime time for commercial electrical maintenance?

The answer is “Yes!” While January marks the official new year, many businesses view September as a fresh start. This makes summer an ideal time for commercial property owners to schedule long-term electrical maintenance projects.
State legislature ends session without passing PLA bill - by Joe Camilo

State legislature ends session without passing PLA bill - by Joe Camilo

Massachusetts taxpayers dodged a bullet when the state Senate didn’t take up legislation passed by the House in the waning moments of the legislative session that would have made it easier for municipalities and state agencies to use union-only project labor agreements (PLAs) on construction projects.
The design-build advantage: Integrated interior design solutions - by Parker Snyder

The design-build advantage: Integrated interior design solutions - by Parker Snyder

When it comes to corporate interior spaces for both commercial and industrial projects, partnering with a design-build firm with in-house interior design services can offer clients many benefits. Unlike traditional delivery methods where interior designers operate independently from the design and construction teams, often creating a longer project timeline as cost negotiations and revisions ensue
Ask the Electrician:  How do I prepare my commercial building for a disaster?

Ask the Electrician: How do I prepare my commercial building for a disaster?

New England’s notorious weather – from fierce winter storms to summer squalls and fall hurricanes – can leave businesses in the dark. While power outages are often blamed on storms, they can also be caused by unforeseen events like accidents or construction mishaps. While it’s impossible to prevent disasters and power outages entirely, proactive preparation can significantly minimize their impact on your commercial building.