Abbot completes multi-phase restoration and repair project at 10 Milk Street and 294 Washington Street

10 Milk Street,
Boston, MA

 

294 Washington Street,
Boston, MA

 

Boston, MA Abbot completed a multi-phase restoration and repair project involving two high-rise connected commercial ornamental historic buildings located at 10 Milk St. and 294 Washington St. in downtown. Collaborating with the engineering firm of CBI Consulting, Inc. the design/build team was able to conduct all of required repairs and renovations while working closely with the city’s Landmarks Commission to preserve the historic integrity of the buildings. 

Phase 1: June 2016 – Dec. 2016
The first phase of the project took place at the back left corner of the Spring Lane side of 294 Washington St. This phase consisted of demolition of the brick corner from the roof to the ground to expose the steel column. Following demolition, Abbot repaired the deteriorated steel in the column and rebricked the corner to match the existing brick. Abbot also conducted other repairs on the back wall and the interior light well. 

Phase 2: March 2017 – March 2018
Phase 2 of the project focused on the Milk St. building face and courtyard. This phase began with of removal of the ornamental 4-foot terra cotta shelf on the 9th floor, and replacing it with GFRP (fiberglass) replicated to match the original appearance.

Importantly, it was determined through inspection that the terra cotta had deteriorated and was debonding from the building. Based on the engineer’s recommendation, it was decided to remove the entire terra cotta shelf to expose the structural steel, and then repair the structural steel, adding new steel framing and a pressure-treated wood top. The finished appearance of the shelf was then replicated with GFRP (fiberglass) panels to match the original shelf. 

A significant complication of this phase was providing a mock-up of the shelf to the Landmarks Commission for approval of the appearance and color of the finished shelf. The GFRP was mechanically anchored to the new plywood framing and the seams were sealed. Because the fiberglass surface was very smooth, it was necessary to anchor a series of snowguards on the surface to provide pedestrian safety from falling snow.

On the Milk St. side of the building, Abbot also replaced the right brick corner from the 3rd to 10th floors, repaired the deteriorated steel, and replaced the brick to match the original color. Located next to this location is modern office building whose loading platform abutted the work area. To allow access to the loading platform while the work was ongoing, Abbot cantilevered over the platform to allow erection of the scaffolding. The corner and shelf was then removed and replaced as described.

Phase 3: March 2018 – Jan. 2019
Phase 3 involved the Washington St. building. This phase was extremely complicated due to heavy pedestrian traffic underneath. Here, Abbot built a structural walkway over the front of the building to cover the width of the sidewalk. The scaffolding was then erected on the face of the building above the structural walkway to the height of the terra cotta shelf. A further complexity concerned erection of the portion of the scaffolding on the right side of the front elevation of the building where the glass canopy that provided natural light where the entrance to the State St. MBTA station was located. It was necessary to remove the masonry above the canopy and install structural steel to cantilever over the glass. The steel provided a platform to protect the glass, and allowed erection of the scaffolding above the canopy to access the right side of the building. The 9th floor shelf was then removed and replaced as in Phase 2.

MORE FROM Construction Design & Engineering

Nobis Group awards Robinson and Moreira STEM scholarships

Concord, NH Nobis Group, a 100% employee-owned consulting firm specializing in engineering and environmental solutions across the Northeast, has named the recipients of its 2025 STEM Scholarship: Andie Moreira of
READ ON THE GO
DIGITAL EDITIONS
Subscribe
Columns and Thought Leadership
Careers in Construction Month focus on training and safety - by Joe Camilo

Careers in Construction Month focus on training and safety - by Joe Camilo

October is Careers in Construction Month, and rarely has it been more consequential. According to our chapter’s national parent organization, the construction industry needs to attract half-a-million new workers in the coming year to meet demand. Addressing that need is a huge job, but we at ABC MA are trying to do our part.
The rise of incubators and co-working spaces: The latest in life sciences - by Matt Combs

The rise of incubators and co-working spaces: The latest in life sciences - by Matt Combs

In recent years, the life science industry has witnessed a shift in how companies operate and innovate. One of the key driving forces behind this transformation is the emergence of incubators and co-working spaces specifically tailored to meet the unique budget and schedule needs of startups.
Ask the Electrician: Is summer a prime time for commercial electrical maintenance?

Ask the Electrician: Is summer a prime time for commercial electrical maintenance?

The answer is “Yes!” While January marks the official new year, many businesses view September as a fresh start. This makes summer an ideal time for commercial property owners to schedule long-term electrical maintenance projects.
The design-build advantage: Integrated interior design solutions - by Parker Snyder

The design-build advantage: Integrated interior design solutions - by Parker Snyder

When it comes to corporate interior spaces for both commercial and industrial projects, partnering with a design-build firm with in-house interior design services can offer clients many benefits. Unlike traditional delivery methods where interior designers operate independently from the design and construction teams, often creating a longer project timeline as cost negotiations and revisions ensue