Abbot Building Restoration completes comprehensive masonry repair project at 75 Kneeland St. in downtown Boston

Boston, MA Abbot Building Restoration has completed a comprehensive façade repair project on a high-rise commercial building located at 75 Kneeland St. in downtown.  Abbot was awarded the contract following a competitive bidding process among multiple masonry contractors in the local area.

The 14-story building is constructed of brick and precast stone – the bottom four floors of precast stone and the upper floors are a blend of stone and brick with precast panel insets and sills. The project focused on the elevation at the intersection of Kneeland and Hudson Sts.

Based on the plan developed by the architectural firm of Walker Consultants, Abbot first erected built-up pipe staging on the full length of the elevation, and then performed the following repairs:

• Pressure washed the entire façade;

• Patched horizontal concrete and sills throughout the building as necessary;

• Caulked all expansion joints and windows;

• Replaced a total of 40 steel lintels;

• Tuck pointed and replaced brick as necessary;

• Replaced a total of 24 precast sills;

• Wet glazed windows as necessary; and

• Applied two coats of Conpro Lastic waterproof elastomeric coating (Conproco Corp., Dover, NH) to the bottom two precast stone floors formulated to match the existing color.

Among the major challenges that Abbot faced were the unknowns involved in determining how best to work within the system in light of the COVID-19 pandemic. The project was delayed from its outset in March until the city allowed work to resume at the beginning of June. Enforcing all COVID-19 related rules provided a further impediment beyond the normal jobsite safety protocols.

Abbot provides a broad range of masonry construction services to public, institutional, and commercial clients, including condominiums, property management entities, and private residences. The firm also acts as a general contractor for a variety of masonry building construction projects.

MORE FROM Construction Design & Engineering
Construction Design & Engineering

Weston & Sampson earns award from ACEC for Arlington DPW job

Arlington, MA Weston & Sampson Engineers, Inc., has earned a National Recognition Award for exemplary engineering achievement in the American Council of Engineering Companies’ (ACEC) 58th annual Engineering Excellence Awards (EEA). The award comes for leading the renovation of the Arlington Department of Public Works (DPW) facility.
READ ON THE GO
DIGITAL EDITIONS
Subscribe
Columns and Thought Leadership
State legislature ends session without passing PLA bill - by Joe Camilo

State legislature ends session without passing PLA bill - by Joe Camilo

Massachusetts taxpayers dodged a bullet when the state Senate didn’t take up legislation passed by the House in the waning moments of the legislative session that would have made it easier for municipalities and state agencies to use union-only project labor agreements (PLAs) on construction projects.
Ask the Electrician: Is summer a prime time for commercial electrical maintenance?

Ask the Electrician: Is summer a prime time for commercial electrical maintenance?

The answer is “Yes!” While January marks the official new year, many businesses view September as a fresh start. This makes summer an ideal time for commercial property owners to schedule long-term electrical maintenance projects.
Ask the Electrician:  How do I prepare my commercial building for a disaster?

Ask the Electrician: How do I prepare my commercial building for a disaster?

New England’s notorious weather – from fierce winter storms to summer squalls and fall hurricanes – can leave businesses in the dark. While power outages are often blamed on storms, they can also be caused by unforeseen events like accidents or construction mishaps. While it’s impossible to prevent disasters and power outages entirely, proactive preparation can significantly minimize their impact on your commercial building.
The design-build advantage: Integrated interior design solutions - by Parker Snyder

The design-build advantage: Integrated interior design solutions - by Parker Snyder

When it comes to corporate interior spaces for both commercial and industrial projects, partnering with a design-build firm with in-house interior design services can offer clients many benefits. Unlike traditional delivery methods where interior designers operate independently from the design and construction teams, often creating a longer project timeline as cost negotiations and revisions ensue